|
|
Tank Rehabilitation

Bates Engineering
designs many new tanks. As a result our clients regularly ask us
to review their tanks designed by us and others. The review
typically culminates in a report which includes recommendations
for improvements and repair. Examples of recent projects
that Bates Engineering has completed from review through
construction are listed below. |

Completed access
house at the
City of Fort Collins 4 MG Reservoir. |
Fort
Collins Utilities Reservoir Improvements
In
1995, the City of Fort Collins, Colorado contracted with Bates
Engineering to review all of their system reservoirs to determine
necessary improvements. The reservoir system at that time consisted
of two concrete 15 MG "hopper bottom" reservoirs at the Water
Treatment Facility constructed in the 1960's and a two-cell rectangular
concrete 4 MG reservoir near the Colorado State University stadium
constructed in the 1980's. Bates Engineering made observations
both from a raft and the dry reservoirs and provided the City
with reports including repair and improvement recommendations.
Bates prepared bid documents to carry out these recommendations.
In 1996, the City approached Lillard and Clark
construction about providing construction services in the City's
modified design/build process for $600,000. Work was carried out
from 1996 to 1998. Work included:
-
Site access improvements including
regarding, placement of base course and new concrete stairways
-
Doubling the size of one access
house to provide a disinfection clean room
-
Providing new doors, recoating
of steel surfaces, halogen lighting and a fall protection system
in all access houses
-
Valve vault improvements including
an enlarged hatch, lighting and heating
-
Installing 10 new 5'x 8' aluminum
hatches on concrete risers through the roofs for light, ventilation
and access
-
Installing one-half mile of 4-inch
PVC washdown piping to facilitate annual cleaning of the reservoirs
-
Various concrete repairs including
polyurethane injection of leaking joints and sealant replacement.
Due to the difficult floor geometry, roof repairs were made
by the contractor from a floating platform inside the tank
At this time, Bates Engineering was
also asked to make a recommendation for coating the 4 MG Reservoir
roof which has experienced significant structural cracking. Bates researched 17 coating products
for the City and evaluated each product based on nine weighted
criteria which were believed to be important to the success of
the project including constructibility, serviceability, durability
and cost. Three of these products were selected
for further evaluation. Bates arranged with three coating contractors
to apply test sections to the reservoir roof. After one year in
place, Bates evaluated the coatings and made a final coating selection.
In 2000, Bates prepared bid documents to complete this work.
|

Baffle details in
the City of Fort Collins, Colorado 15 MG Reservoirs |
In 1997 the City
asked Bates Engineering to perform a hydraulic
model study. The study conducted at the Bureau of Reclamation
Hydraulics Laboratories in Denver developed efficient baffle systems
to increase contact time in the two short-circuiting 15 MG Reservoirs.
Bates designed Hypalon baffles that were installed by Lillard and
Clark Construction in 1998. The City's subsequent fluoride tracer
tests verified the efficacy of the baffle systems. This study was
included in an AWWA Research Foundation study report and won the
American Consulting Engineers Council of Colorado Excellence Award for Studies in 2000. |
Rafter replacement
in the City of Longmont 6 MG Tank |
City
of Longmont 6 MG Steel Reservoir
| In 1997 the City
of Longmont, Colorado asked Bates Engineering to evaluate two of
their reservoirs including their 6 MG steel reservoir. Bates performed
both a floating and a dry review. Bates Engineering contracted with
a nondestructive testing service to evaluate steel thickness in
the floor and roof and a tank testing service to perform magnetic
flux testing of the floor. Bates had the interior and exterior coatings
tested for lead, chromium and cadmium. Significant levels of lead
were found both in the interior and exterior coating systems. A
complete report with photographs was presented to the City making
repair and improvement recommendations. |
Bates prepared bid documents for the work
which included the following items:
-
Site grading and access improvements
-
Replacement of three 36-inch butterfly
valves in the valve vault
-
Recoating the reservoir including removal
or overcoating of lead-based paints
-
Removing and replacing 30 corroded
roof rafters
-
Lowering the height of the overflow
piping to avoid wetting of the roof rafters
-
Providing safety rails around the inlet
pipe and floor drain
- Designing a new caged exterior ladder with locking
cover and landing
-
Providing two new 5' x 8' roof access
hatches with safety railing
-
Adding a new 30-inch-diameter manhole
including a concrete washdown pad outside the tank and reinforcing
the steel floor inside the tank to protect from traffic damage
-
Verifying the results of the magnetic
flux testing by cutting and repairing coupons from the tank floor
plate
Bates provided regular field observation
during the construction and provided construction administration services
to the City.
|

Completed East Vail
Meadow Tank |
Eagle
River Water and Sanitation District
500,000 Gallon East Vail Meadows Tank
Between 1996 and
1998, Eagle River Water and Sanitation District in Vail, Colorado asked
Bates Engineering to review and prepare bid documents to repair three
of their system reservoirs including two concrete tanks located on Vail
Mountain. The concrete tank repairs included removing a damaged lining
from one tank and shotcreting the underside of the roof of the other.
Both tanks received new roof hatches and a new ladder. Due to the difficult
terrain, Bates reviewed one site by snowmobile. Construction access
required the use of track vehicles.
| The 500,000 Gallon East Vail Meadows
steel tank is located at the east end of Vail in an active avalanche
chute. Due to the high value of downhill residences, the City asked
Bates Engineering to retrofit the tank to mitigate damage due to
the presence of the tank and stored water during a 100-year avalanche
event. Because stiffening the tank was believed to exceed the replacement
value of the tank, Bates designed retrofit anchor bolts to secure
the tank to its concrete foundation for the loads due to this 17-foot-deep
avalanche. In addition to specifying the new interior and exterior
coatings, Bates also recommended cathodic protection system repairs,
designed a new access ladder and helped the District select aluminum
clad insulation to replace badly vandalized insulation. Construction
was completed in 1999. |
|
|