Bates Engineering, Inc.



25 MG Foothills Reservoir

DW 25 MG Foothills Reservoir

Construction for the 385.5-foot-diameter Denver Water 25 million gallon Reservoir No. 3 was completed in June 2002. This project was awarded the Rocky Mountain Chapter American Concrete Institute Award of Excellence, in May 2002.

 


Interesting Statistics About the Reservoir

Concrete:

10,500 cubic yards

Prestressing Steel:

1,002,000 feet or about 190 miles

      Floor Slab:

224,000 feet
      Wall:
480,000 feet
      Roof Slab:
298,000 feet
Excavation:
about 250,000 cubic yards

Area:

2.8 acres

Volume:

3,989,438 cubic feet or 29,840,996 gallons

Operational Volume:

25,040,000 gallons



As concrete events go, this was among the biggest. On December 2, 400 people working as well-organized team completed one of the largest single-day pours in the history of Colorado construction. The 120,000-sq-ft. slab at Denver Water Department's Fourteen Reservoir #3, located a few miles south of Chatfield Reservoir, required 3,240 cu. yds. of concrete poured and finished in a 14-hour period.

The pour according to Steve Thanner, construction manager for the water and wastewater division of Centric-Jones Constructors, the general contractor on the project,

 

the massive pour was completed "without a hitch." Thanner credits everyone involved, especially the planning of Mike Leister at the Denver Water Dept. and the engineers, Bob Bates of Bates Engineering and Diana Horner of Plains Engineering.

The pour required 65 trucks and 128 people from Aggregate Industries, the concrete provider, whose drivers logged more than 10,500 miles on the project. Brundage Bone handled the pumping, and more than 100 people from Laursso Concrete did the finish work. The slab is the base of a 25-million-gal. tank that will eventually

 
replace treated water storage the water department lost due to upgrades at two other plants. The tank should be complete in late 2001.

Article courtesy of F.W. Dodge Colorado Construction, A Publication of The McGraw-Hill Companie
s


Huge concrete pour raises logistical challenges, attracts crowd.

How many concrete trucks does it take to continuously deliver and pour 3,300 yd. (3,000 m3) of concrete into a hole in the ground about the size of a football stadium? The question was not a trivial matter when Denver Water began laying plans to build a 25-mil-gal (95 × 103m3) underground water reservoir for its Foothills Water Treatment Plant west of Denver. The storage tank—the biggest circular post-tensioned concrete water storage tank west of the Mississippi River—posed challenges that required 31/2 months of preparations.


Article courtesy of AWWA


The project design was performed by Plains Engineering, Inc. and Bates Engineering, Inc.