As
concrete events go, this was among the biggest. On December
2, 400 people working as well-organized team completed one of the largest
single-day pours in the history of Colorado construction. The 120,000-sq-ft.
slab at Denver Water Department's Fourteen Reservoir #3, located a few
miles south of Chatfield Reservoir, required 3,240 cu. yds. of concrete
poured and finished in a 14-hour period.
The pour according to Steve Thanner, construction manager
for the water and wastewater division of Centric-Jones Constructors,
the general contractor on the project, |
|
the massive pour was completed
"without a hitch." Thanner credits everyone involved, especially
the planning of Mike Leister at the Denver Water Dept. and the engineers,
Bob Bates of Bates Engineering and Diana Horner of Plains Engineering.
The pour required 65 trucks and 128 people from Aggregate
Industries, the concrete provider, whose drivers logged more than 10,500
miles on the project. Brundage Bone handled the pumping, and more than
100 people from Laursso Concrete did the finish work. The slab is the
base of a 25-million-gal. tank that will eventually |
|
replace treated water storage the water department lost due to upgrades
at two other plants. The tank should be complete in late 2001. |